Environmental Process

Our team is developing an Environmental Impact Statement (EIS) for the Grand Crossing Rail Project. Federal law requires that an EIS be prepared for federally-funded projects that could potentially affect the quality of the human and natural environment. When it is complete, the EIS will explain the solution that will best address the transportation issues and then detail how this solution was decided. The EIS will explain the potential impacts and benefits resulting from the project and identify ways to avoid or lessen the negative impacts. The EIS will also describe how the public was engaged in the decision-making process and how the local community's concerns and values were factored into the proposed solution.

Parts of the EIS

Purpose and Need: This section of the study document explains why the Grand Crossing Rail Project is needed and the specific transportation needs that the project is trying to address. It also includes information about transportation facilities in the project study area. The public plays an important role in developing these needs and identifying the problems, and the project team will continue to listen to and integrate public input into this section.

Alternatives: This section explores possible solutions to the transportation problems posed in the Purpose and Need. It explains how reasonable alternatives were selected for study and the reasons why some were eliminated from consideration. It may also identify the alternative that best solves these transportation problems (i.e., the preferred alternative) and explain the basis for that decision. This section includes input from the public and local community members, who will have opportunities to comment on the proposed and preferred alternatives.

Affected Environment: This section describes the existing human and natural environmental settings in the project study area. This includes a description of the resources that may be affected by the project including residences, businesses, community facilities, recreational areas, historic resources, streams and wetlands, and plant and animal species. This information is compiled through research, environmental studies, and community input.

Environmental Effects: This section describes the potential impacts and benefits that each of the alternatives would have on the environment and the actions recommended to avoid, minimize, or mitigate these impacts. Information in this section is used to compare the alternatives carried forward.

Comments and Coordination: This section summarizes the public involvement process for the project including public meetings, community advisory groups, presentations to block clubs and business associations, and other outreach activities. It details comments received from the public and responses to those comments. It also explains the resource and regulatory agency coordination that took place, any comments received, and how agency comments were addressed.

Environmental Impact Statement Schedule

The EIS process involves the following steps:

  1. The process formally began with a Notice of Intent in March 2011.
  2. The Draft Purpose and Need is prepared. Public input on the Purpose and Need was gathered at two Public Meetings in December 2011 and at a Community Meeting in May 2012.
  3. Proposed Alternatives were developed. The public provided input on the proposed reasonable Alternatives at a second round of Public Meetings in March 2012.
  4. Alternatives were evaluated.
  5. The findings of the technical studies; impacts and benefits; measures to mitigate any negative effects for the project; and public input will be documented in the Draft EIS. A Public Hearing will be held after the Draft EIS is published to formally present the findings of the Draft EIS and receive comments.
  6. Based on comments and review of the Draft EIS, a Preferred Alternative for the project will be included in the Final EIS.
  7. The Record of Decision will complete the EIS process.

The Draft Environmental Impact Statement for this project has not been completed. Additional project funding is required to advance this project through the planning, design, and construction phases. The Project Team is currently working to secure funding in connection with the project's purpose and need without compromise to the existing and future passenger rail service in the area. As a result of these issues, a definitive project timeline cannot be provided. Thank you for your continued interest and please check back for project updates and future activities.